ENEE Installs 30-Megawatt Transformer in Santa Rosa

Published on Honduras Daily · Jun 9, 2026 · Originally reported June 8, 2026 by Radio Cadena Voces (X)

The state power utility is installing a 30-megawatt transformer at the Santa Rosa de Copán substation (more than 50 million lempiras, roughly $2 million) and building a 5-kilometer transmission line to ease low-voltage problems affecting thousands of customers across Copán, Lempira, and Ocotepeque.