Quebrada de Agua
Scheduled power cuts for Quebrada de Agua.
Upcoming cuts
Friday, September 18
- 8:00 a.m. – 4:00 p.m.
Tocoa
Substation: Bonito OrientalCircuit BOR-L351General line maintenance.
32 areas affected
Las UvasResidencia Prado VerdeDoctoresCorporación Dinant (Exportadora del Atlántico)Quebrada de ArenaTocoaSan José del CincoSalamáLa AbisiniaEl BrichePalmichalSalomón 1 y 2BomberosLa 45Quebrada de AguaToronjalLa 15El NovilloFabio OchoaHospital San IsidroAlemán 2LaurelesParte de CorocitoJuan AntonioLa ArenosaSan José de CorralesLa Nueva Suyapa18 de SeptiembreEl BarroAuroraTaujicaEl Tigre
Past cuts
Recent outages recorded for this area.
Wednesday, September 2
- 8:30 a.m. – 4:30 p.m.Past
Tocoa
Substation: Bonito OrientalCircuit BOR-L351General maintenance on transmission line L516 TEL-SIS.
35 areas affected
Las UvasColonias y Barrios ToronjalDoctoresCorporación Dinant (Exportadora del Atlántico)Quebrada de ArenaSan José del CincoSalamáTauticaCorocitoLa AbisiniaEl BrichePalmichalRes. Prado VerdeSalomón 1 y 2La AdeñozaLa Nueva SuayapaEl 15BomberosLa 45Quebrada de AguaEl NovilloFabio OchoaHospital San IsidroAlemán 2LaurelesParte de CorocitoJuan AntonioLa ArenosaSan José de CorralesLa Nueva Suyapa18 de SeptiembreEl BarroTauicaAuroraEl Tigre
Wednesday, August 12
- 8:30 a.m. – 4:30 p.m.Past
Tocoa
Substation: Bonito OrientalCircuit BOR L351Maintenance on transmission lines L520 (RGU-ISL) and L521 (ISL-TOC) 138 kV
6 areas affected
Wednesday, July 29
- 8:00 a.m. – 5:00 p.m.Past
Tocoa
Substation: Bonito OrientalCircuit BOR-L351Scheduled maintenance on the 138 kV L515 transmission line (PGR-GUA-TEL).
20 areas affected
Tuesday, July 21
- 8:00 a.m. – 4:00 p.m.Past
Tocoa
Substation: Bonito OrientalCircuit BOR-L351General circuit maintenance and trunk circuit repowering.
20 areas affected